## Información del Proyecto
|
||
|
||
- **Cliente**: AJETHAI CO., LTD. (Tailandia)
|
||
- **Proyecto**: 169423.A.2.2
|
||
- **Alcance**: Reemplazo de flowmeters (80000SEV909, 80000SEV081 & 80000SEV079)
|
||
- **Máquina**: Mixer STARBLEND PLUS D7 # SSAE0340
|
||
- **Valor**: €56,017 / €23,450.40
|
||
- **Referencia**: E5.007172
|
||
|
||
## Cronología de Eventos
|
||
|
||
### **Septiembre 2024**
|
||
|
||
- **02/09/2024**: Cliente emite POs:
|
||
- PO #38204 (Partes)
|
||
- PO #38205 (Intervención)
|
||
|
||
### **Octubre 2024**
|
||
|
||
- **25/10/2024**: Fecha de entrega comprometida (CRD)
|
||
- **Octubre**: Gestión de términos de pago
|
||
- Negociación de términos: cambio de "within a week" a 30 días
|
||
- Confirmación: 100% del precio total pagadero dentro de 30 días
|
||
|
||
### **Noviembre 2024**
|
||
|
||
- **06/11/2024**: Fecha FCA Parma confirmada
|
||
- **Noviembre**: Lanzamiento del proyecto
|
||
- Estado: LAUNCHED
|
||
- PM Supply asignado: Pietro Bruno
|
||
- Creación de SO (Sales Order)
|
||
|
||
### **Proceso de Ejecución**
|
||
|
||
#### **Fase de Planificación**
|
||
|
||
- **Project Manager Supply**: Pietro Bruno (inicial) → Luca Di Gioia (reasignado)
|
||
- **Services Project Manager**: Remi Courtiade
|
||
- **Coordinación Regional**: Chaiwat Amnuaisin
|
||
|
||
#### **Desarrollo y Validación**
|
||
|
||
- **Risk Assessment**: Completado con puntos específicos para PM Service
|
||
- **DV (Delivery Validation)**: Organizada por la zona
|
||
- Propósito: Verificar condiciones de la máquina antes de la intervención
|
||
- Razón: Información limitada de mantenimiento, posibles modificaciones locales del cliente
|
||
|
||
#### **Problemas Técnicos Identificados**
|
||
|
||
- **Software Backup**: Ingeniero en sitio detecta diferencias entre:
|
||
- Software presente en la máquina
|
||
- Software enviado previamente por el cliente
|
||
- **Acción requerida**: Alessandro Passera (TD) debe verificar si las diferencias afectarán la instalación
|
||
|
||
#### **Factory Acceptance Test (FAT)**
|
||
|
||
- **Resultado**: FAT exitoso
|
||
- **Status**: Mercancías listas en planta de Parma
|
||
- **Documentos**: Preparados para organizar recogida
|
||
|
||
#### **Gestión de Envío**
|
||
|
||
- **Método**: Flete aéreo (airfreight)
|
||
- **Logística**: Coordinación con Geodis para determinar si usar DHL
|
||
- **Costos de embalaje**: Añadidos al PO
|
||
|
||
### **Puntos Críticos del Proyecto**
|
||
|
||
#### **Riesgos Identificados**
|
||
|
||
1. **Carga de trabajo actual** y **escasez de materias primas**
|
||
2. **Componentes eléctricos** principalmente afectados
|
||
3. **Modificaciones locales** del cliente en la máquina
|
||
|
||
#### **Información Técnica Requerida**
|
||
|
||
- **PLC software backup** (más importante para cambio de flowmeters)
|
||
- **Fotos de cables y conectores** de los flowmeters
|
||
- **Verificación de compatibilidad** de cables existentes
|
||
|
||
#### **Timeline de Instalación**
|
||
|
||
- **Planificación**: Instalación prevista en 4 semanas desde la comunicación
|
||
- **Pendiente**: Confirmación de fecha específica con cliente
|
||
- **Coordinación**: Con equipo de planificación para asignación de ingeniero
|
||
|
||
### **Estado Final (09/06/2025)**
|
||
|
||
- **Comunicación de Alessandro Passera**:
|
||
- No hay archivo adjunto en el email
|
||
- Esperando software backup para comparación de versiones
|
||
- **Próximos pasos**: Verificación de compatibilidad de software antes de la instalación
|
||
|
||
## Actores Principales
|
||
|
||
|Nombre|Rol|Responsabilidad|
|
||
|---|---|---|
|
||
|**Remi Courtiade**|Services Project Manager|Gestión general del proyecto|
|
||
|**Luca Di Gioia**|Project Manager Supply|Suministro y coordinación|
|
||
|**Pietro Bruno**|Project Manager Supply (inicial)|Lanzamiento del proyecto|
|
||
|**Alessandro Passera**|Technical Department|Verificación de software|
|
||
|**Chaiwat Amnuaisin**|Regional Coordinator|Coordinación con cliente|
|
||
|**Cholpassorn Thananakruangsri**|Services PM Assistant|Documentación y POs|
|
||
|
||
## Lecciones Aprendidas
|
||
|
||
- Importancia de la validación previa (DV) en proyectos con información limitada de mantenimiento
|
||
- Necesidad de verificación exhaustiva de software antes de la instalación
|
||
- Coordinación efectiva entre equipos técnicos y comerciales para gestión de riesgos
|
||
|
||
|
||
|
||
|
||
|
||
|
||
|
||
|
||
# Índice de Mensajes
|
||
|
||
- 09-06-2025 - Passera, Alessandro - [[Cronología del Proyecto 169423 - AJETHAI CO., LTD.#R: NOTICE OF GOODS READY ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172|R-NOTICE-OF-GOODS-READY-ASSIGN-ORDER-169423---Won-Opportunity---Services--169423A22---AJETHAI-CO-LTD---Thailand---Filling---Service-CRM0037299CHECK-PAYMENT-TERME5007172]]
|
||
|
||
---
|
||
|
||
+ 168205d5e00fbfeebaf1eadffd340445
|
||
|
||
### R: NOTICE OF GOODS READY ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
- 09-06-2025
|
||
|
||
Dear all, into the email was not present any file attached .
|
||
In order to compare the software version we will wait the software backup.
|
||
Best regards
|
||
|
||
Alessandro PASSERA
|
||
Tel: +39 0521 999 319
|
||
Mob: +39 3459439668
|
||
Fax : +39 0521 999511
|
||
www.sidel.com
|
||
|
||
General
|
||
|
||
Ciao Alessandro,
|
||
An engineer went on site to make the DV and notice some differences on the software present on the machine and the software that customer sent us.
|
||
Please find in attached the software backup that the engineer sent.
|
||
Can you please check that the differences will not create issue on the new software, and in case it’s need correct the new software.
|
||
|
||
Many thanks
|
||
Best Regards,
|
||
LUCA DI GIOIA
|
||
PROJECT MANAGER SUPPLY
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Mail:
|
||
|
||
General
|
||
|
||
Hello Luca,
|
||
Any update on this topic?
|
||
Thanks in advance,
|
||
Best regards.
|
||
Remi
|
||
|
||
General
|
||
|
||
***
|
||
Subject: RE: NOTICE OF GOODS READY ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Dear Luca,
|
||
We will make the installation of this project in 4 weeks.
|
||
|
||
Did the TD update you about the last version of the software backup send by the engineer. Will it impact the installation?
|
||
Thanks in advance,
|
||
Best regards.
|
||
Remi
|
||
|
||
***
|
||
Subject: R: NOTICE OF GOODS READY ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Dear Remi,
|
||
I’ll check with TD.
|
||
Many thanks
|
||
Best Regards,
|
||
LUCA DI GIOIA
|
||
PROJECT MANAGER SUPPLY
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Mail:
|
||
|
||
General
|
||
|
||
Hello Luca,
|
||
An engineer went on site to make the DV and notice some differences on the software present on the machine and the software that customer sent us.
|
||
Please find in attached the software backup that the engineer sent.
|
||
Can you please check that the differences will not create issue on the new software, and in case it’s need correct the new software.
|
||
Thanks in advance,
|
||
Best regards.
|
||
Remi
|
||
|
||
General
|
||
|
||
***
|
||
Subject: R: NOTICE OF GOODS READY ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Dear Remi,
|
||
please could you me update on the pick up of the goods ?
|
||
|
||
Many thanks
|
||
Best Regards,
|
||
LUCA DI GIOIA
|
||
PROJECT MANAGER SUPPLY
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Mail:
|
||
|
||
General
|
||
|
||
Dears
|
||
Please see attached the documents recap.
|
||
|
||
Many thanks
|
||
Best Regards,
|
||
LUCA DI GIOIA
|
||
PROJECT MANAGER SUPPLY
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Mail:
|
||
|
||
|
||
Dear Remi,
|
||
Please find attached the revised PO with packing cost for your reference.
|
||
|
||
Best regards,
|
||
Cholpassorn Thananakruangsri (Ang)
|
||
|
||
Services Project Management Assistant
|
||
Sidel Group
|
||
Sidel South Asia-Pacific Ltd.,
|
||
|
||
18th Floor (Zone C, D, E), Thanapoom Tower,
|
||
1550 New Petchburi Rd, Makkasan,
|
||
|
||
Rajthevee, Bangkok 10400, Thailand
|
||
www.sidel.com
|
||
|
||
Discover our online Option & Upgrade catalogue @
|
||
www.options-upgrades.sidel.com
|
||
|
||
General
|
||
|
||
***
|
||
Subject: RE: NOTICE OF GOODS READY ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Hello Ang,
|
||
Can you please help to modify the PO in attached and add the packing cost.
|
||
|
||
For the shipment we will go by airfreight so no need to modify the delivery address.
|
||
Thanks in advance,
|
||
Best regards.
|
||
Remi
|
||
|
||
General
|
||
|
||
***
|
||
Subject: RE: NOTICE OF GOODS READY ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Hello Luca,
|
||
I am checking with Geodis if we will used DHL or not this shipment.
|
||
As soon as I have the answer, I will validate the draft invoice or modified the PO.
|
||
Have a nice day,
|
||
Best regards.
|
||
Remi
|
||
|
||
***
|
||
Subject: R: NOTICE OF GOODS READY ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Dear Remy,
|
||
please could you validate and align the PO to the draft ?
|
||
thanks
|
||
Many thanks
|
||
Best Regards,
|
||
LUCA DI GIOIA
|
||
PROJECT MANAGER SUPPLY
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Mail:
|
||
|
||
General
|
||
|
||
Dear Remi,
|
||
|
||
please see attached the draft invoice to validate to proceed with final invoice.
|
||
|
||
Please align the Po with the draft.
|
||
I’m waiting your feedback
|
||
|
||
Many thanks
|
||
Best Regards,
|
||
LUCA DI GIOIA
|
||
PROJECT MANAGER SUPPLY
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Mail:
|
||
|
||
Dear Remi,
|
||
FAT with positive exit of the goods has been done.
|
||
Please see attached the documents to organize the pick-up.
|
||
The goods are ready in Parma plant.
|
||
|
||
Many thanks
|
||
Best Regards,
|
||
LUCA DI GIOIA
|
||
PROJECT MANAGER SUPPLY
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Mail:
|
||
|
||
Dear Remi
|
||
I’ll check and I’ll revert you asap
|
||
Please take note that project has been reassigned to
|
||
@Di Gioia, Cosimo Luca
|
||
s
|
||
|
||
Sara Signorini
|
||
Project Management Supply Manager
|
||
Line Solution Projects
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Tel.: +39 0521 999 761
|
||
General
|
||
|
||
Hello Sara,
|
||
As my email to Pietro didn’t reach him can you please help on this project?
|
||
Thanks in advance,
|
||
Best regards.
|
||
Remi
|
||
|
||
General
|
||
|
||
Passera, Alessandro <Alessandro.Passera@sidel.com>; Amnuaisin, Chaiwat <Chaiwat.Amnuaisin@sidel.com>
|
||
|
||
***
|
||
Subject: RE: ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Ciao Pietro,
|
||
Can you please confirm the FCA date on the 06/11/2024.
|
||
Thanks in advance,
|
||
Best regards,
|
||
Remi
|
||
|
||
***
|
||
Subject: R: ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Dears, for change flowmeters the most important info are the PLC software backup.
|
||
Adding on it some picture related the cable and connectors of the Flowmeters in order to check if need new cable or not.
|
||
For automation side we do not need any others details, maybe from mechanical side need more info but you have to refer to the colleague for mechanical
|
||
office.
|
||
Best regards
|
||
|
||
Alessandro PASSERA
|
||
Tel: +39 0521 999 319
|
||
Mob: +39 3459439668
|
||
Fax : +39 0521 999511
|
||
www.sidel.com
|
||
|
||
General
|
||
|
||
Passera, Alessandro <Alessandro.Passera@sidel.com>
|
||
|
||
@Passera, Alessandro
|
||
the zone is organising a DV on its own, for this specific order, do you need the technician who will deal with this DV to check particular areas of the machine in addition to what is already requested in the risk assessment file ?
|
||
Thx
|
||
BR,
|
||
|
||
|
||
Pietro Bruno
|
||
|
||
Project Manager Supply
|
||
Line Solutions Projects
|
||
SIDEL SPA
|
||
|
||
Via La Spezia 241/A, 43126 Parma, ITALY
|
||
Tel:
|
||
+39 0521 999 664
|
||
Mob: +39 345 0689 767
|
||
www.sidel.com
|
||
|
||
General
|
||
|
||
Sacchi, Stefania[External] <Stefania.Sacchi.external@sidel.com>
|
||
|
||
Ciao Pietro,
|
||
We don’t have much maintenance info of this machine, this customer is minimalist. Maintenance has been done by customers, there might be some local
|
||
modification done by customers. To avoid the issue during intervention, we proposed the customer to perform DV. After DV we will propose an overhaul or at least to have customers have our recommended spare parts in the stock.
|
||
In case you have any specific points/ areas related to this project required the FSE to focus / pay special attention during the DV., kindly advice.
|
||
Thank you.
|
||
|
||
Best regards,
|
||
Chaiwat Amnuaisin
|
||
|
||
General
|
||
|
||
Sacchi, Stefania[External] <Stefania.Sacchi.external@sidel.com>
|
||
|
||
***
|
||
Subject: R: ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Ciao Remi,
|
||
Why did you organize a DV?
|
||
I don’t see it specified in the offer and in the risk assessment file.
|
||
BR,
|
||
|
||
|
||
Pietro Bruno
|
||
|
||
Project Manager Supply
|
||
Line Solutions Projects
|
||
SIDEL SPA
|
||
|
||
Via La Spezia 241/A, 43126 Parma, ITALY
|
||
Tel:
|
||
+39 0521 999 664
|
||
Mob: +39 345 0689 767
|
||
www.sidel.com
|
||
|
||
General
|
||
|
||
Passera, Alessandro <Alessandro.Passera@sidel.com>; Sacchi, Stefania[External] <Stefania.Sacchi.external@sidel.com>
|
||
|
||
Ciao Pietro,
|
||
I will ask customer for the software and the video.
|
||
For this project we informed customer that we will make a DV before the installation. Can you please indicate any specific point that need to be check
|
||
and focus.
|
||
For the intervention, no date planned yet, I will check with customer when they want to have it and check with planning team who is available. Once
|
||
I have the engineer’s name we can planned the meeting.
|
||
Have a nice day,
|
||
Best regards.
|
||
Remi
|
||
|
||
General
|
||
|
||
Sacchi, Stefania[External] <Stefania.Sacchi.external@sidel.com>
|
||
|
||
***
|
||
Subject: R: ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==E5.007172
|
||
|
||
Dear Remi,
|
||
PROJECT REFERENCE E5.007172 (Attached you will also find the risk assessment, I ask you to check the points where the PMService is the Owner)
|
||
BR,
|
||
|
||
|
||
Pietro Bruno
|
||
|
||
Project Manager Supply
|
||
Line Solutions Projects
|
||
SIDEL SPA
|
||
|
||
Via La Spezia 241/A, 43126 Parma, ITALY
|
||
Tel:
|
||
+39 0521 999 664
|
||
Mob: +39 345 0689 767
|
||
www.sidel.com
|
||
|
||
General
|
||
|
||
Thanks Pietro, please keep Remi in the loop as he is the SPM assigned for this project. Thank you.
|
||
|
||
Best regards,
|
||
Chaiwat Amnuaisin
|
||
|
||
General
|
||
|
||
***
|
||
Subject: R: ASSIGN ORDER 169423 - Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==
|
||
|
||
Dear Chaiwat,
|
||
PROJECT STATUS : LAUNCHED
|
||
|
||
FCA PARMA DELIVERY DATE 06/11/2024
|
||
PROJECT REFERENCE E5.007172
|
||
BR,
|
||
|
||
|
||
Pietro Bruno
|
||
|
||
Project Manager Supply
|
||
Line Solutions Projects
|
||
SIDEL SPA
|
||
|
||
Via La Spezia 241/A, 43126 Parma, ITALY
|
||
Tel:
|
||
+39 0521 999 664
|
||
Mob: +39 345 0689 767
|
||
www.sidel.com
|
||
|
||
General
|
||
|
||
Bruno, Pietro <Pietro.Bruno@sidel.com>
|
||
|
||
Dear Chaiwat,
|
||
Project : LI_SHORT
|
||
Status of the project : TO BE LAUNCHED
|
||
Scope of Supply: REPLACEMENT OF FLOW METERS 80000SEV909, 80000SEV081 & 80000SEV079
|
||
Machine involved: SSAE0340
|
||
Assigned PMS : PIETRO BRUNO
|
||
ZRD: 06/11/2024
|
||
ESTIMATED PDD FCA PARMA: 06/11/2024
|
||
NOTE: THANKS TO INFORM US ABOUT THE PLANNED INSTALLATION DATE OF THE PROJECT IN SUBJECT AS SOON AS IT WILL BE PLANNED
|
||
IMPORTANT:
|
||
|
||
DUE TO THE ACTUAL WORKLOAD AND RAW MATERIALS SHORTAGE, MAINLY IMPACTING ELECTRICAL COMPONENTS, THE WEEKS
|
||
|
||
INDICATED IN THE OFFER AND PDD ARE AT RISK.
|
||
NEED TO PLAN THE BOM AVAILABILITY DATE, THEN BASED ON SUPPLIERS CONFIRMATIONS WE WILL ADJUST THE TARGET IF NEEDED.
|
||
FOR THE TIME BEING CONSIDER THE ABOVE PLANNING.
|
||
|
||
I remain at your disposal for any further details
|
||
|
||
Kind regards
|
||
Sara
|
||
|
||
Sara Signorini
|
||
Project Management Supply Manager
|
||
Line Solution Projects
|
||
Sidel Group
|
||
Sidel SpA
|
||
Via La Spezia 241/A
|
||
43124 Parma - Italy
|
||
Tel.: +39 0521 999 761
|
||
General
|
||
|
||
Dear Team,
|
||
As Remi is on leave, could you help to manage this order pls?
|
||
We have received the PO for this project.
|
||
SO waiting for Sales admin
|
||
Project no. H5.012882
|
||
Network 5040590
|
||
Material no. EQPT24163
|
||
Internal PO 4501782678
|
||
|
||
CRD 25 Oct 2024
|
||
|
||
| Material no | DESCRIPTION | PRU | 20% |
|
||
|-------------|---------------------------------------|-------------|-------------|
|
||
| EQPT24163 | Flow meters installed on the SSAE0340 | € 19,542.00 | € 23,450.40 |
|
||
| | | TOTAL | € 23,450.40 |
|
||
|
||
I am attaching the following documents:
|
||
|
||
Product offerInternal PO
|
||
Kindly acknowledge the order by return with delivery date.
|
||
Thanks
|
||
|
||
Best regards,
|
||
Chaiwat Amnuaisin
|
||
|
||
General
|
||
|
||
***
|
||
Subject: RE: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==
|
||
|
||
Dear P’Chaiwat/Remi,
|
||
FYI.
|
||
SO waiting for Sales admin
|
||
Project no. H5.012882
|
||
Network 5040590
|
||
Material no. EQPT24163
|
||
Internal PO 4501782678 Leadtime: 25 Oct 2024
|
||
|
||
| Material no | DESCRIPTION | PRU | 20% |
|
||
|-------------|---------------------------------------|-------------|-------------|
|
||
| EQPT24163 | Flow meters installed on the SSAE0340 | € 19,542.00 | € 23,450.40 |
|
||
| | | TOTAL | € 23,450.40 |
|
||
|
||
Best regards,
|
||
Cholpassorn Thananakruangsri (Ang)
|
||
|
||
Services Project Management Assistant
|
||
Sidel Group
|
||
Sidel South Asia-Pacific Ltd.,
|
||
|
||
18th Floor (Zone C, D, E), Thanapoom Tower,
|
||
1550 New Petchburi Rd, Makkasan,
|
||
|
||
Rajthevee, Bangkok 10400, Thailand
|
||
www.sidel.com
|
||
|
||
Discover our online Option & Upgrade catalogue @
|
||
www.options-upgrades.sidel.com
|
||
|
||
|
||
|
||
General
|
||
|
||
***
|
||
Subject: RE: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==
|
||
|
||
Dear Isabelle,
|
||
Could you please create SO under pre-offer no. 211106074?
|
||
Customer PO: 38204 dated: 02.09.2024 for Parts
|
||
38205 dated: 02.09.2024 for intervention
|
||
Note:
|
||
|
||
Payment terms:
|
||
100% of the total contract price shall be paid by bank transfer within 30 days from Sidel invoice date.
|
||
|
||
Thank you.
|
||
Best regards,
|
||
Cholpassorn Thananakruangsri (Ang)
|
||
|
||
Services Project Management Assistant
|
||
Sidel Group
|
||
Sidel South Asia-Pacific Ltd.,
|
||
|
||
18th Floor (Zone C, D, E), Thanapoom Tower,
|
||
1550 New Petchburi Rd, Makkasan,
|
||
|
||
Rajthevee, Bangkok 10400, Thailand
|
||
www.sidel.com
|
||
|
||
Discover our online Option & Upgrade catalogue @
|
||
www.options-upgrades.sidel.com
|
||
|
||
|
||
|
||
Warasin, Woranitcha <Woranitcha.Warasin@sidel.com>
|
||
|
||
***
|
||
Subject: RE: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==
|
||
|
||
Hi Chaiwat,
|
||
|
||
Ajethai is paying at 30 days
|
||
|
||
Best regards.
|
||
|
||
Isabelle Gruchy
|
||
Sales Administration Manager
|
||
Mobile : +33 6 13 18 05 22
|
||
Cash collection/Administrative treatment of Exports Financings
|
||
Sales Administration Dpt
|
||
|
||
General
|
||
|
||
Cc : Courtiade, Remi [EXTERNAL] <remi.courtiade.external@sidel.com>; Thananakruangsri, Cholpassorn <Cholpassorn.Thananakruangsri@sidel.com>;
|
||
Warasin, Woranitcha <Woranitcha.Warasin@sidel.com>
|
||
|
||
Objet : RE: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==
|
||
|
||
Hi Isabelle,
|
||
|
||
Do you agree with the PT? Thanks,
|
||
|
||
Best regards,
|
||
Chaiwat Amnuaisin
|
||
|
||
General
|
||
|
||
***
|
||
Subject: Re: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==
|
||
|
||
Dear P’ Chaiwat,
|
||
|
||
We can offer 30 days credit after shipment because their overdue is clean.
|
||
|
||
Regards,
|
||
|
||
Joy
|
||
|
||
Get Outlook for iOS
|
||
|
||
General
|
||
|
||
***
|
||
Subject: RE: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==
|
||
|
||
Hi N’Ang,
|
||
The credit 30 days should be at in our payment term, so changing from within a week to 30 days.
|
||
@Warasin, Woranitcha
|
||
Can you confirm pls?
|
||
Thanks.
|
||
|
||
Best regards,
|
||
Chaiwat Amnuaisin
|
||
|
||
General
|
||
|
||
Warasin, Woranitcha <Woranitcha.Warasin@sidel.com>
|
||
|
||
***
|
||
Subject: RE: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299==CHECK PAYMENT TERM==
|
||
|
||
Dear P’Chaiwat,
|
||
Could you please confirm the payment term?
|
||
Thank you ka.
|
||
|
||
Best regards,
|
||
Cholpassorn Thananakruangsri (Ang)
|
||
|
||
Services Project Management Assistant
|
||
Sidel Group
|
||
Sidel South Asia-Pacific Ltd.,
|
||
|
||
18th Floor (Zone C, D, E), Thanapoom Tower,
|
||
1550 New Petchburi Rd, Makkasan,
|
||
|
||
Rajthevee, Bangkok 10400, Thailand
|
||
www.sidel.com
|
||
|
||
Discover our online Option & Upgrade catalogue @
|
||
www.options-upgrades.sidel.com
|
||
|
||
|
||
|
||
General
|
||
|
||
***
|
||
Subject: FW: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299
|
||
|
||
Hello N’Ang,
|
||
On behalf of Remi, could you help to register this order pls?
|
||
ID Invoice: 1767954
|
||
ID delivery: 1767954
|
||
Machine: Mixer STARBLEND PLUS D7 # SSAE0340
|
||
CRD: 25-Oct-2024
|
||
PO No. Material PO #38204. I&C PO #38205
|
||
|
||
PM Fee: 2,054 Eur
|
||
|
||
|
||
|
||
Attaching customer PO (x2), offer from BU, Final offer submitted to customer and Costing table.
|
||
Thank you krub
|
||
|
||
Best regards,
|
||
Chaiwat Amnuaisin
|
||
|
||
General
|
||
|
||
Warasin, Woranitcha <Woranitcha.Warasin@sidel.com>;
|
||
Courtiade, Remi [EXTERNAL] <remi.courtiade.external@sidel.com>;
|
||
Strzerzynski, Cyril <cyril.strzerzynski@sidel.com>
|
||
|
||
***
|
||
Subject: Won Opportunity - Services- 169423.A.2.2 - AJETHAI CO., LTD. - Thailand - Filling - Service CRM:0037299
|
||
|
||
Obs- obsolescence FillingAJETHAI CO., LTD.169423.A.2.2 - FIL_OCM001 NEw EH Flow Meter for Mixer -
|
||
|
||
Offer link
|
||
Services Manager:
|
||
Woranitcha Warasin
|
||
o
|
||
Project Manager: Remi Courtiade
|
||
o
|
||
Opportunity Amount: 56 017 €
|
||
Reason for winning:
|
||
Any Other Reason
|
||
o
|
||
Reason for winning 2:
|
||
o
|
||
Winning comments:
|
||
o
|
||
Competitor: NO COMPETITOR
|
||
o
|
||
Competitor value:
|
||
o
|
||
Reasons for customer investment: Replacement
|
||