Eurotronica FM-C UC 130/15K #SRVU0008
Replacement of the current MMF201 agitator (V_7800/TF201 code 174147) with that of the new supplier AERRE-INOX
Component List

CHAPTER A:
New installation assembly (04321052302) for new AERRE-INOX mixer 00000225909.
# AUTOMATION & ELECTRICAL MATERIALS.
# KMT-08 TORQUE WRENCH (SIDEL REF. 00000234046) TO SCREW THE NUT SECURING BUSHING MM10cad14-T.
AERRE-INOX 3.1 CERTIFICATE according to EN10204 - material in contact with food product

# CHAPTER E :
00000265159, IMPELLER FOR MAGNETIC MIXER AMT-12: with Dynamic bearing made of Tungsten Carbide West
AERRE-INOX 3.1 CERTIFICATE according to EN10204 - material in contact with food product 

# CHAPTER S : 
SPARE PARTS KIT, 00000260552 KMT-08-AT, FOR MIXER 00000225909 TMI2AC: Static bearing MIMS + Seal for static bearing 40TFM + Fixing screw MM.

!20250320_091355[1].jpg

!Pasted image 20250320125038.png

!Pasted image 20250320161833.png

!Pasted image 20250320161852.png

Offer


ORANGINA SUNTORY FRANCE PRODUCTION

France

Offer

Replacement of the current MMF201 agitator (Y_7800/TF201: code 174147) with that of the new supplier AERRE-INOX.

Quotation N° Revision Date Comments
170511 1 3/20/2025 Initial

FOR

Machine Serial N°
Eurotronica FM-C UC 130/15K SRVU0008
Service project engineer:

 Andrea Parri
Tel: Andrea.Parri@sidel.com
Service Project Manager:

Moutairou Aline
Tel: +49 152 545 795 39 Aline.Moutairou@sidel.com

CONTENT

1     MACHINES INVOLVED......................................................................................................................... 3

2     PROPOSAL DESCRIPTION.................................................................................................................. 4

2.1       Project description.................................................................................................................... 4

2.1.1        Our technical solution........................................................................................................ 5

2.1.2        Installation, startup and commissioning.............................................................................. 6

2.2       Critical to project [CTP]............................................................................................................. 8

3     COMMERCIAL PROPOSAL.................................................................................................................. 8

3.1       Costs of Supply........................................................................................................................ 8

3.2       Proposal validity....................................................................................................................... 8

3.2.1        Expiration......................................................................................................................... 8

3.2.2        Requirements................................................................................................................... 8

3.3       Samples.................................................................................................................................. 8

1       MACHINES INVOLVED

This proposal concerns all the following machines

 

MACHINE Eurotronica FM-C UC 130/15K #SRVU0008 Combi#510
MODEL Filler Eurotronica FMC UC_SRVU
SERIAL NUMBER (fref. in offer) SRVU0008_A
YEAR OF CONSTRUCTION 2012
INSTALLATION PLANT DONNERY
MACHINE Eurotronica FM-C UC 130/15K #SRVU0008 Combi#510
MODEL Filler Eurotronica FMC UC_SRVU
SERIAL NUMBER (fref. in offer) SRVU0008_E
YEAR OF CONSTRUCTION 2012
INSTALLATION PLANT DONNERY
MACHINE Eurotronica FM-C UC 130/15K #SRVU0008 Combi#510
MODEL Filler Eurotronica FMC UC_SRVU
SERIAL NUMBER (fref. in offer) SRVU0008_F
YEAR OF CONSTRUCTION 2012
INSTALLATION PLANT DONNERY
MACHINE Eurotronica FM-C UC 130/15K #SRVU0008 Combi#510
MODEL Filler Eurotronica FMC UC_SRVU
SERIAL NUMBER (fref. in offer) SRVU0008_S
YEAR OF CONSTRUCTION 2012
INSTALLATION PLANT DONNERY

 

 

 

2       PROPOSAL DESCRIPTION

2.1      Project description

Customer request:

The Customer wants to replace the current product agitator, identified by the SIDEL code 00000174147 (MSB10/200) and identified at HMI by the classification criterion MMF201, which is installed on the product storage tank (TF201) of the SRVU0008.

2.1.1      Our technical solution

 

CHAPTER A. Replacement of the current MMF201 agitator (Y_7800/TF201: code 174147) with new BY AERRE-INOX.

SIDEL's O&U technical department has carried out a study to verify the replacement of the current mixer/agitator with that of a different supplier (which is our new supply standard).

In the study we considered the assembly of the magnetic mixer, identified by the SIDEL code 00000225909 (TM12AC), from the supplier AERRE-INOX.

The study was also used to evaluate the dimensions and any obstacles that could be present during the replacement; we had asked Aline Moutairou and SAM Teil Herve to receive photos of the area where the agitator is installed, to verify that there are no piping made differently from what is present in CAD but, we did not receive the photos.

Current mixer installed (00000174147) on Current Product Feeding Assembly (Y_7800: 04291736906):

Currently, SRVU0008 has installed, on the product storage tank (TF201), the magnetic mixer from the supplier Mariotti&Pecini, MSB10/200, flanged.

The electric motor (component 1) has a size of 0.75 Kw.

New agitator to be installed (00000225909):

Comparing the new agitator with the current one, it can be noted that the interaxis and the number of holes on the flange are the same.

Therefore, installation on the storage tank is possible: furthermore, the external dimensions are similar.

Like the agitator currently present, the electric motor of the new one also has a power of 0.75 Kw.

The new magnetic agitator has an average LT, of the supplier to SIDEL, of 9 working weeks.

Since there are no elements nearby (e.g. piping) that can generate interference, the assembly of the new agitator is possible without modifying additional components.

(however, we have not received the photos to confirm the real situation of the piping on site)

In addition to offering the new agitator 00000225909, in order to correctly install the new impeller and, for future maintenance, it is needed and offered:

KMT-08 TORQUE WRENCH (SIDEL REF. 00000234046) TO SCREW THE NUT SECURING BUSHING MMxx-xx/14-T.

Fix the Drive unit “Pin” procedure=

With the tool KMT-08 as in evidence here below (GREEN arrow), tighten the drive unit at 20 N/m as data below.

Please SECURE that the PTFE gasket were not out of the bushing following the tighten procedure.

ATTENTION:

The replacement of the agitator must be done by specialized personnel and, first, the work environment must be made safe.

The tank and the pipes must be drained and the supply of the various gases must be interrupted (possibly, applying a padlock to the interception valves to avoid accidental opening).

ON SITE=

1 Mechanical operator Sidel for 1 day

1 Electricia operator Sidel for 2 day

1 Automation operator Sidel for 3 day. To check the setup and the correct direction of rotation of the impeller. The THIRD day are used to check the CIP and Production cycle.

1 customer operator.

CHAPTER “E”.  EMERGENCY SPARE PART FOR HIGH LEAD TIME: impeller TM12, CODE 00000265159. LT = about 8 WEEKS.  OPTIONAL.

SIDEL recommends that the customer keep one impeller in its spare parts warehouse.

The impeller assembly cannot be repaired on site (the bushing inside the impeller cannot be replaced on site): to repair/overhaul the impeller assembly, it will need to be shipped to SIDEL/AERRE-INOX.

We offer=

·         00000265159, IMPELLER FOR MAGNETIC MIXER AMT-12, with:

o     Dynamic bearing made of Tungsten Carbide Wc+Ni.

o    Surface roughness average Ra 0,2 µm.

o    Extimate LT form supplier for SIDEL= about 8 WORKING WEEKS.

·         AERRE-INOX 3.1 CERTIFICATE according EN10204 - material in contact with food product.

The cost of the impeller's overhaul will be discussed in a separate chapter.

CHAPTER “F”. Overhaul of the impeller, performed by the supplier AERRE-INOX, managed by Sidel S.p.A_IT_Parma. Optional / When needed.

In this chapter the cost necessary to overhaul the impeller of the MIXER-agitator product of the NEW supplier AERREINOX is quoted.

In this specific case, to overhaul the "TM12 / 4-T" impeller model (A-R code), identified by the SIDEL code: 00000265159.

The impeller assembly cannot be repaired on site (the bushing inside the impeller cannot be replaced on site): to repair/overhaul the impeller assembly, it will need to be shipped to SIDEL/AERRE-INOX.

The cost of the overhaul refers to the invoicing of AERREINOX to Sidel S.p.A_IT_Parma.

The overhaul will be performed only and only at the Italian factory of the Aerreinox supplier.

The cost of the impeller revision, is budget.

If the customer deems it necessary, for the supply of the revised impeller or any maintenance kit from the AERREINOX supplier, he can request the certificate of suitability for contact with food in accordance with EN10204 or FDA.

The certificate has a cost. If it should be requested separately from the order of the material (after the order), it will have a double cost.

In this chapter, I enter the average cost of the certificate, requested together with the ordered material.

NOTES ON THE MANAGEMENT OF THE IMPELLER OVERHAUL:

In the event that the bottler customer is in Italy and is not yet a customer of AERREINOX, and wants to directly manage the review with AERREINOX, the company would apply the commercial conditions relating to new customers: advance payment to the order.

In the event that the bottler customer is located outside Italy, and wants to manage the maintenance independently, he will have to rely on the Aerre Inox dealer in that country.

Below you will find the link of the official AERRE INOX dealers: https://www.aerreinox.it/rete-di-vendita.

In the specific case of this French customer, the local supplier is the company: Poliflux.

In 2021 I had contacted the supplier Poliflux for another French project and the outcome was that the most economical solution is to manage the maintenance through SIDEL and not through the local dealer of Aerre-Inox.

CHAPTER “S”. SPARE PARTS KITS FOR THE NEW AERRE-INOX MIXER 00000225909 TM12AC. OPTIONAL.

We offer the SPARE PARTS KIT, 00000260552 KMT-08-AT, FOR MIXER 00000225909_TM12AC, composed by:

Static Tungsten Carbide bearing MM8 + PTFE Seal for static bearing 40TFM + Fixing screw MM.

2.1.2      Installation, startup and commissioning

Estimation of the men power to carry out the installation on site (travel days excluded):

 

SRVU0008_A - Installation Men Days on site Skill
Mechanical 1 1 MECHANICAL L3 PRODUCT SUPPORT ENGINEER
Electrical 1 2 ELECTRICAL L3 PRODUCT SUPPORT ENGINEER
Software 1 3 AUTOMATION L3 PRODUCT SUPPORT ENGINEER

 

 

 

DETAILED PLANNING FOR INSTALLATION

 

 

2.2      Critical to project [CTP]

 

Item Title Description Needs Check
1 DV/EV need to check the machine status and the specific parts of it to be modified applicable for machine very old, in case of complex modification or under specific request from ETO V
2 Pictures/Photos equipment parts pictures to support BOM development applicable only when DV is not requested, detail the request in the offer depending on project type V
3 SW backup request to customer the software backup, PLC + HMI applicable for projects involving automation and electrical modifications V
4 Caps/Bottles/Product samples request samples needs clearly highlighting the quantity (units or liters), specifying if it is a bottle, a cap or product applicable for projects which impacts on the filling, handling capping process or in case of new products to be filled
5 Prototype Modules part of the existing filler is a prototype or remained a prototype to highlight if any part of the existing filler remained a prototype
6 Critical Installation installation to be done with high skilled Senior Specialist (or FSE well prepared by ETO), ETO will specify the skills requested applicable for complex modification or in case the machine is old or unknown V
7 Unknown or not clear supplier or supply lead time low visibility on the supplier and LT of some parts of the scope; check with PM Supply before confirming the LT if order is taken the supplier and/or the part/component lead time is not defined
8 Testing activities additional tests to be done with LT not defined; check with PM Supply before confirming the LT if order is taken solution can be tested by Sidel to ensure assembly or functioning or both
9 Innovative/Critical  solution or within the Top Issues perimeter additional tests to be done with LT not defined; check with PM Supply before confirming the LT if order is taken solution never designed, critical or under analysis inside the top issues perimeter

3       COMMERCIAL PROPOSAL

3.1      Costs of Supply

 

A1 - Machine SRVU0008_A RSP Price (EUR)
1. Component list

New installation assembly (04321052302) for new AERRE-INOX mixer 00000225909.

AUTOMATION & ELECTRICAL MATERIALS.

KMT-08 TORQUE WRENCH (SIDEL REF. 00000234046) TO SCREW THE NUT SECURING BUSHING MMxx-xx/14-T.

AERRE-INOX 3.1 CERTIFICATE according EN10204 - material in contact with food product.

2. Packing & Crating

Packing cost
23,648.00

(detail of this cost already present in the total: €47)

709.00
TOTAL: MATERIAL

Parma

Lead time ready to ship: 12 working weeks
24,357.00

 

 

A2 - Machine SRVU0008_E OPTIONAL. RSP Price (EUR)
1. Component list

00000265159, IMPELLER FOR MAGNETIC MIXER AMT-12: with Dynamic bearing made of Tungsten Carbide Wc+Ni.

AERRE-INOX 3.1 CERTIFICATE according EN10204 - material in contact with food product.

2. Packing & Crating

Packing cost
5,514.00

(detail of this cost already present in the total: €47)

165.00
TOTAL: MATERIAL

Parma

Lead time ready to ship: about 8 working weeks
5,679.00

 

 

A3 - Machine SRVU0008_F OPTIONAL, When needed. RSP Price (EUR)
1. Component list

Overhaul of the impeller, performed by the supplier AERRE-INOX.

AERRE-INOX 3.1 CERTIFICATE according EN10204 - material in contact with food product.

2. Packing & Crating

Packing cost
4,166.00

(detail of this cost already present in the total: €47)

125.00
TOTAL: MATERIAL

Parma

Lead time ready to ship: BUDGET 12 working weeks
4,291.00

 

 

A4 - Machine SRVU0008_S OPTIONAL. RSP Price (EUR)
1. Component list

SPARE PARTS KIT, 00000260552 KMT-08-AT, FOR MIXER 00000225909 TM12AC: Static bearing MM8 + Seal for static bearing 40TFM + Fixing screw MM.

2. Packing & Crating

Packing cost
1,366.00

41.00
TOTAL: MATERIAL

Parma

Lead time ready to ship: 8 working weeks
1,407.00

 

3.2      Proposal validity

3.2.1      Expiration

The Offer is valid sixty (60) days from the date thereof. Extension of the Offer is subject to Sellers written approval. After this period, prices can be revised.

Any express reference to the data of this offer (number/date) that will be included in the Purchase Order issued by customer shall be intended as acceptance by the customer of the whole content of this offer, including the attached Sidel's General Conditions of Contract, and as prevalence of this offer on any other possible contract conditions text that may be sent by the customer.

3.2.2      Requirements

The present offer is only valid if the machines object of our proposal meets the following requirements:

§  They comply with the technical documentation in our possession.

§  They are in a good condition of maintenance.

§  On the machines are installed original components supplied by the manufacturer.

We kindly ask the buyer to inform us on possible differences in comparison the above.

In case of order, it will be care of the buyer to send us a copy of the electrical diagram, a copy of the software installed on the machine to be modified and the different samples mentioned in the table here under (Paragraph “Mandatory technical specification & samples”).

3.3      Samples

All below technical specification & samples are mandatory for ordering.

 

PRODUCT CLAUSE:

Customer will supply samples of products, exiting from the production line and at the contractual output, for commissioning purposes.

Should our staff have to wait, because the buyer is not in a position to feed our equipment with the right products, then the waiting time would be charged extra at our usual daily rate.

FDM RVU008 E5.007382

FDM Name Replacement of the current MMF201 agitator
FDM Number 0001 Date 11/02/2025
Affaire RVU008, E5.007382-EXMU01UF, EQPT24640
Master Eplan 2.8 -> Creata revisione 14 di schema el.
Author Santini Paolo
BOM MODIFICATION
Numero modifica lancio 819109
Pilota Generale EQPT24640
Pilota Elettrico  (NFT) 43760381
Materiale Elettrico (NFT) 43760384
Materiale test/programmazione E5.00xxxx  (NFT) 43760386
Etichetta Elettrica (NFT) 43760403
Schema Elettrico (PEA) 43760405
Pilota Originale Macchina  04291428601
Numero Modifica Aggiornamento Pilota 819128
EPLAN P5 -> EPLAN 2.8 Codici Archiviazione Revisioni
Numero modifica creazione versione 01.
Disegno elettrico numero.
Numero modifica creazione versione 02.
Numero modifica creazione versione 03.
Numero modifica creazione versione 04.
Numero modifica creazione versione 05.
Numero modifica creazione versione 06…XX

FDM DESCRIPTION

Per uniformità di progetto verrà evaso un inverter FC302 al posto del FC280.            (Comunicazione al PM 11/02/2025).

1-   Pag.055 Inserito nuovo inverter su rete profibus.

2-   Pag.0140 Aggiunto comune 140X5/22A.

3-   Pag.0200 Nuovo inverter per agitatore.

4-   Pag.0925 Consensi safety per nuovo inverter.

5-   Pag.0927 Eliminato vecchio comando agitatore.

6-   Pag.0950 Eliminato fbk del vecchio 200K7.

7-   Pag.0962 FBK morsetto 27 inverter agitatore.

8-   Pag.1240 Aggiornato lay out Q.E. Dalle misure arrivate da cantiere linverter si posiziona precisamente nelle spazio indicato. Forniamo pezzo di canala da 25mm per sostituire la canala da 40 presente nel caso di problemi.

-Nota per il tecnico cablatore : Controllare sempre il materiale evaso in distinta ( sotto allegata ) e

                                             portare con se il materiale di consumo e lattrezzatura necessaria per               

                                          la corretta realizzazione dellUpgrade.

-Note for the cabling technician : Always check the processed material in the list ( attached below )

                                            and bring with you the consumables and equipment necessary for

                                           the correct implementation of the Upgrade.

In caso di sotituzione inverter ripetere tutte le prove di arresto in emergenza (con verifica rampe) e nel caso motore macchina anche di marcia jog con porte chiuse e porte aperte.

If the inverter is replaced, repeat all the emergency stop test (whit ramp check) and, in the case of the machine motor, also the jog running tests whit doors closed and doors open.